| Project |
Name |
Grant Program |
Agency |
Date Of Approval |
Dollar Amount |
Dollar Spent Or Date Obligated |
| 1 |
Maple Avenue Reconstruction |
STP* |
KKCOM |
September-05 |
$356,500 |
2013 |
| 2 |
Golfview Hazard Monroe Reconstruction |
STP |
KKCOM |
January-06 |
$1,659,000 |
$1,659,000 |
| 3 |
Golfview Highlands Unit 8 Reconstruction |
CDBG |
Kane County |
March-06 |
$235,000 |
$235,000 |
| 4 |
Maple Avenue Reconstruction |
TARP |
IDOT |
January-07 |
$123,600 |
2013 |
| 5 |
RT 31 and Huntley Road Intersection Improvements |
CMAQ |
CMAP |
July-07 |
$3,324,800 |
2014 |
| 6 |
Washington Street Resurfacing |
LAPP |
KKCOM |
June-08 |
$120,000 |
$120,000 |
| 7 |
2007 Street Program Street Lighting |
DCEO |
State of Illinois |
December-08 |
$40,000 |
$40,000 |
| 8 |
2010 Area Reconstruction Project |
CDBG |
Kane County |
March-09 |
$149,952 |
$149,952 |
| 9 |
Golfview Hazard Monroe Reconstruction |
CDBG |
Kane County |
March-09 |
$263,478 |
$263,478 |
| 10 |
Washington Street Resurfacing |
ARRA |
KKCOM |
March-09 |
$160,000 |
$160,000 |
| 11 |
Maple Avenue Reconstruction |
ARRA |
KKCOM |
March-09 |
$273,518 |
2013 |
| 12 |
2010 Resurfacing Program Various Streets |
ERP |
IDOT |
September-09 |
$300,000 |
$300,000 |
| 13 |
Helm Road Roadway and Drainage Improvements |
ERP |
IDOT |
September-09 |
$280,000 |
$280,000 |
| 14 |
Jack Hill Park Pedestrian Path |
Riverboat |
Kane County |
September-09 |
$20,000 |
$20,000 |
| 15 |
Maple Avenue Bikepath and Roadway Lighting Project |
ITEP |
IDOT |
December-09 |
$374,770 |
2013 |
| 16 |
Golfview Hazard Monroe Reconstruction |
STP* |
KKCOM |
March-10 |
$831,800 |
$831,800 |
| 17 |
2010 MFT / CDBG Resurfacing |
CDBG |
Kane County |
July-10 |
$181,000 |
$148,161 |
| 18 |
Golfview Hazard Monroe Reconstruction |
IDOT |
IDOT |
July-10 |
$180,201 |
$180,201 |
| 19 |
2011 MFT / CDBG Resurfacing |
CDBG |
Kane County |
May-11 |
$158,859 |
$158,859 |
| 20 |
Carpenter Park North Parking Lot Expansion |
CDBG |
Kane County |
May-11 |
$109,389 |
2012 |
| 21 |
2012 Tulsa Avenue / Kings Road Resurfacing |
LAPP |
KKCOM |
June-11 |
$413,094 |
2012 |
| 22 |
Canoe / Emergency Rescue Boat Launch |
Riverboat |
Kane County |
July-11 |
$19,700 |
$19,700 |
| 23 |
Road Repairs (For 2012 In-house Resurfacing Program) |
DCEO |
State of Illinois |
November-11 |
$50,000 |
2012 |
| 24 |
RT 31 and Huntley Road Intersection Improvements |
TARP |
IDOT |
January-12 |
$74,150 |
2014 |
*supplemental grant
GRANTS PENDING - Submitted for review and approval
| Project |
Name |
Grant Program |
Agency |
Status |
Dollar Amount |
Date To Be Spent |
| 1 |
Roadway, Utility Improvements |
DCEO |
State of Illinois |
In review |
$190,000 |
TBD |
| 2 |
Street Lighting |
DCEO |
State of Illinois |
In review |
$250,000 |
TBD |
| 3 |
Old Town Bicycle Path Improvements |
Riverboat |
Kane County |
In review |
$74,646 |
2013 |
| 4 |
South Lincoln Avenue Pedestrian Improvements |
Riverboat |
Kane County |
In review |
$37,725 |
2013 |
| 5 |
2012 MFT / CDBG Resurfacing |
CDBG |
Kane County |
In review |
$148,035 |
2012 |
| 6 |
2012 MFT / CDBG Sidewalk and Resurface |
CDBG |
Kane County |
In review |
$242,043 |
2012 |
| 7 |
Fairview Park Improvements |
CDBG |
Kane County |
In review |
$278,500 |
TBD |
| 8 |
Maple Avenue Reconstruction |
TARP* |
IDOT |
In review |
$144,300 |
2013 |
*supplemental grant
|
|